An RFI asks for clarification of project information. Use this template to prepare the question and its evidence, then route it through your project's existing review and issue process.

  1. Check for an existing answer.

    Review the current drawings, specification and RFI register first. Record what you checked. If the uncertainty remains, choose one decision for this draft.

  2. Show the difference.

    State the location and the two records or observations that do not align. Include exact references and enough marked-up context for the respondent to find the same point.

  3. Request a usable response.

    Ask precisely what needs confirmation. State when the work needs the information, and have the reviewer agree the formal response date and recipient. Retain unknown impacts as unknown.

Your blank template

Copy the fields into your notes, or download a file to keep with your project records.

DRAFT REQUEST FOR INFORMATION
Project:
Draft reference / version / prepared by:
Subject:
Location / work package / activity:

CURRENT REFERENCES
Document / revision / page or detail:
Other relevant reference:
Attachments / marked-up extracts:
Existing RFI or response checked:

BACKGROUND
What do the supplied records show?
What remains unclear?

QUESTION
Please confirm [one decision or missing detail].

RESPONSE NEEDED
Requested date / reason:
Reviewer to confirm respondent and formal due date:

IMPACTS
Cost: [Not assessed / evidenced description]
Programme: [Not assessed / evidenced description]
Assumptions or information still missing:

REVIEW
Prepared by:
Checked by / date:
Issued in project system as:
Official response / reference / date:
Required follow-up after response:
What belongs in each field?
Identity
Project, draft reference, preparer and concise subject.
Location and package
Where the question applies and which activity or package needs the answer.
References
Drawing numbers/revisions, specification sections, relevant responses and attachment IDs.
Background
The observed discrepancy and the records already checked.
Question
One clear request for the information or decision needed.
Timing
Requested response date and reason, subject to the project's review process.
Impacts
Known cost/programme implications with evidence, or explicitly not yet assessed.
Review and response
Reviewer, intended respondent, issued reference and official response record.

See what a useful record looks like

Filled example: clarify a cabinet tag

Fictional documents and dates. This is an example question, not an engineering instruction.

Project: Harbour Pump Station (fictional) Draft: RFI-D-014 | Subject: North plantroom cabinet tag Location: cabinet beside door N-02 References: layout E-204 revision C, detail 2; equipment schedule ES-01 revision B, row 14; photos P-01 and P-02. Background: the layout labels this cabinet CP-02. The equipment schedule and visible cabinet label read CP-03. No existing response was found in the register checked for this example. Question: please confirm the correct equipment tag for this cabinet and identify the document reference to use in the handover register. Requested response: 22 September 2026, ahead of the planned register review; formal due date to be agreed by the RFI manager. Cost/programme impacts: not assessed. Status: draft for project-engineer review.

Before you issue it

  • Is the requested decision clear without opening an unrelated email chain?
  • Is every drawing number, revision, location and attachment correct?
  • Does the question distinguish an observed discrepancy from an assumed cause?
  • Have cost and programme impacts remained unconfirmed unless supported?
  • Has the reviewer checked the recipient, requested date and existing responses?
  • Will the official response be retained and linked to the resulting follow-up?

If you use AI to help draft

Use this instruction with references you are authorised to share, then check the resulting draft yourself.

Using only the supplied references, draft a concise RFI with background, one question and missing information. Preserve every document number and revision. Do not propose a technical solution, invent a response deadline or assign cost/programme impacts. Keep uncertain information explicit. Return a draft for the project engineer to review.

Scope and sources

  • The Digital Hardhat does not issue or answer the formal RFI for your project. Use the authorised project system and review process.
  • A draft RFI is not an instruction to change the works. Contract notices, approval and technical decisions remain with the responsible project professionals.

Our original template helps prepare a question. The linked documentation provides workflow context; it does not establish your project's contractual requirements.

  • Procore: Create an RFI

    Primary documentation covering the question, supporting context, references, impacts and draft/review workflow.

  • Procore: Draft an RFI with Procore AI

    Product documentation explicitly requires review of AI output. The page labels the feature open beta as checked on 20 September 2026; access depends on the account setup.

Suggest a correction or a missing field

Put it to work

Capture the evidence in a field note

Keep photos, location and the observed discrepancy together in the Field Note Analyzer. Transfer the checked references into this template and your project's RFI system. This tool is not an RFI generator.

Open the tool